작업현장에서는 작은 실수가  사람의 생명을 앗아가거나 치명적인 상해를 가할 수 있기 때문에 철저한 주의가 요망됩니다.

Bumble Bee의 끔찍한 사고로 근로자가 죽음을 당한 사건이 다시는 일어나지 않기를 바라며~

 

Lock out Tagout을 철저히 관리하면, 많은 사고를 예방할 수 있으리라 생각합니다.

아래 참고하세요. 그리고 좀 더 자세한 Lockout Tagout에 대한 정보는 별첨을 열어보시기 바랍니다.

 


• Part Number: 1910
• Part Title: Occupational Safety and Health Standards
• Subpart: J
• Subpart Title: General Environmental Controls
• Standard Number: 1910.147 App A
• Title: Typical minimal lockout procedures


General

The following simple lockout procedure is provided to assist employers in developing their procedures so they meet the requirements of this standard. When the energy isolating devices are not lockable, tagout may be used, provided the employer complies with the provisions of the standard which require additional training and more rigorous periodic inspections. When tagout is used and the energy isolating devices are lockable, the employer must provide full employee protection (see paragraph (c)(3)) and additional training and more rigorous periodic inspections are required. For more complex systems, more comprehensive procedures may need to be developed, documented, and utilized.

Lockout Procedure

Lockout Procedure for

________________________

(Name of Company for single procedure or identification of equipment if multiple procedures are used).

Purpose

This procedure establishes the minimum requirements for the lockout of energy isolating devices whenever maintenance or servicing is done on machines or equipment. It shall be used to ensure that the machine or equipment is stopped, isolated from all potentially hazardous energy sources and locked out before employees perform any servicing or maintenance where the unexpected energization or start-up of the machine or equipment or release of stored energy could cause injury.

Compliance With This Program

All employees are required to comply with the restrictions and limitations imposed upon them during the use of lockout. The authorized employees are required to perform the lockout in accordance with this procedure. All employees, upon observing a machine or piece of equipment which is locked out to perform servicing or maintenance shall not attempt to start, energize, or use that machine or equipment.

________________________

Type of compliance enforcement to be taken for violation of the above.

Sequence of Lockout

(1) Notify all affected employees that servicing or maintenance is required on a machine or equipment and that the machine or equipment must be shut down and locked out to perform the servicing or maintenance.

________________________

Name(s)/Job Title(s) of affected employees and how to notify.

(2) The authorized employee shall refer to the company procedure to identify the type and magnitude of the energy that the machine or equipment utilizes, shall understand the hazards of the energy, and shall know the methods to control the energy.

________________________

Type(s) and magnitude(s) of energy, its hazards and the methods to control the energy.

(3) If the machine or equipment is operating, shut it down by the normal stopping procedure (depress the stop button, open switch, close valve, etc.).

________________________

Type(s) and location(s) of machine or equipment operating controls.

(4) De-activate the energy isolating device(s) so that the machine or equipment is isolated from the energy source(s).

________________________

Type(s) and location(s) of energy isolating devices.

(5) Lock out the energy isolating device(s) with assigned individual lock(s).

(6) Stored or residual energy (such as that in capacitors, springs, elevated machine members, rotating flywheels, hydraulic systems, and air, gas, steam, or water pressure, etc.) must be dissipated or restrained by methods such as grounding, repositioning, blocking, bleeding down, etc.

________________________

Type(s) of stored energy - methods to dissipate or restrain.

(7) Ensure that the equipment is disconnected from the energy source(s) by first checking that no personnel are exposed, then verify the isolation of the equipment by operating the push button or other normal operating control(s) or by testing to make certain the equipment will not operate.

Caution: Return operating control(s) to neutral or "off" position after verifying the isolation of the equipment.

________________________

Method of verifying the isolation of the equipment.

(8) The machine or equipment is now locked out.

Restoring Equipment to Service. When the servicing or maintenance is completed and the machine or equipment is ready to return to normal operating condition, the following steps shall be taken.

(1) Check the machine or equipment and the immediate area around the machine to ensure that nonessential items have been removed and that the machine or equipment components are operationally intact.

(2) Check the work area to ensure that all employees have been safely positioned or removed from the area.

(3) Verify that the controls are in neutral.

(4) Remove the lockout devices and reenergize the machine or equipment.

Note: The removal of some forms of blocking may require reenergization of of the machine before safe removal.

(5) Notify affected employees that the servicing or maintenance is completed and the machine or equipment is ready for use.

[54 FR 36687, Sept. 1, 1989 as amended at 54 FR 42498, Oct. 17, 1989; 55 FR 38685, Sept. 20, 1990; 61 FR 5507, Feb. 13, 1996]

 

http://www.osha.gov/pls/oshaweb/owadisp.show_document?p_id=9805&p_table=STANDARDS

No. Subject Author Date Views
38 Employment Transaction Form HR Consultant 2012.02.04 1235
37 Written Warning Form 1 HR Consultant 2012.02.04 1251
36 Verbal Warning Form HR Consultant 2012.02.04 1285
35 Direct Deposit Form admin 2012.02.04 1305
34 Warning Form 2 HR Consultant 2012.02.04 1313
33 Evaluation Form - 360 degree HR Consultant 2012.02.18 1352
32 Separation Form HR Consultant 2012.02.04 1358
31 W-9 Form admin 2011.12.24 1423
30 Employee Payroll Deduction Form admin 2012.02.04 1423
29 I-9 Form Spanish admin 2011.12.24 1436
28 I-9 Form English admin 2011.12.24 1466
27 W-4 Form admin 2011.12.24 1503
26 Calinfornia Exemption Worksheet admin 2012.02.04 1519
25 UI Form - CA HR Consultant 2012.02.04 1557
24 Exit Interview - Sample Questions admin 2011.12.24 1614
23 CA State - Paid Family Leave Information HR Consultant 2012.03.24 1622
22 Confidentiality Agreement - Employee HR Consultant 2012.02.04 1624
21 Exit Interview Questions - Form Attached Admin 2012.03.31 1646
20 ADA Form HRConsultant1 2012.09.16 1921
19 FMLA Form HR-Consultant 2012.07.02 1925